7. Termination and Suspension

The Contractor’s failure to fully and timely perform its obligations under the Contract Documents or to strictly comply with terms and conditions of the Contract Documents shall constitute default of the Contractor; in such event, the District may terminate the Contract upon seven (7) days written notice to the Contractor. Unless the Contractor commences, and diligently thereafter prosecutes to completion, all required actions to cure such default(s), the Contract is deemed terminated without further action of the District; such termination shall be effective the seventh (7th) day after the date of the District’s written notice. If the District terminates the Contract for default of the Contractor, the Contractor and the Performance Bond Surety are liable to the District for all losses, costs and damages arising out of the Contractor’s default and costs to complete the Project Work which exceeds the remaining Contract Price at the time of termination.

The District may terminate the Contract, in whole or in part, at any time for the convenience of the District by written notice to the Contractor, in which case, the payment of the Contract Price shall be limited to the value of the Work in place or in progress at the time of the termination for the District’s convenience; no payment shall be made or due from the District for the unperformed portion of the Project Work.

The District may by written directive to the Contractor, suspend the Project Work, in whole or in part, for such time as determined by the District. Upon issuance of such directive, the Contractor shall take action as directed to protect work in place, materials/equipment at the Site and other actions relating to Project Work in place, in progress, in storage, in transit or in fabrication (“Contractor Suspension Activities”). The Contractor shall resume Project Work as directed by the District. The District’s suspension of Project Work shall not result in adjustment of the Contract Price, except for the direct costs of Contractor Suspension Activities. The Contract Time will be equitably adjusted for District directed suspension of Project Work.