4. Contract Price

If the Contract Time is sixty (60) days or less, the District will make payment of the Contract Price upon completion of the Project, the Contractor’s full performance of all other obligations under the Contract Documents and the Contractor’s submission of a properly itemized invoice and duly executed Verification of Certified Payroll Records Submittal to Labor Commissioner. Upon receipt of thereof, the District Representative will promptly verify that the Project has been completed and that the Contractor has performed all other obligations hereunder. Within thirty (30) days of the District Representative confirmation of the completion of Work and the Contractor’s performance of other obligations hereunder, the District will make payment of the Contract Price.

If the Contract Time is sixty (60) days or more, the Contractor may submit invoices on a monthly basis for the value of Project Work completed in the prior month, whereupon the District Representative will promptly verify that the Work has been completed as indicated in the Contractor’s invoice. Within thirty (30) days after District’s approval of the Application for Payment, Contractor shall be paid a sum equal to ninety-five percent (95%) of the value of the Work performed (as verified by the District and certified by Contractor) up to the last day of the previous month, less the aggregate of previous payments and amount to be withheld. Within sixty (60) days of completion of all Project Work and all other of the Contractor’s obligations hereunder, amounts previously retained from prior invoices will be released to the Contractor. The District may, in its sole discretion, condition payment of the Contract Price, or any portion thereof, upon: (i) the Contractor’s preparation of a Schedule of Values for review and acceptance by the District’s Representative; (ii) the submittal of executed Waivers and Releases (on Progress Payment or Final Payment, as applicable) for the Contractor and all Subcontractors receiving any portion of the Contract Price; and/or (iii) delivery of Certified Payroll records of the Contractor and Subcontractors.

Pursuant to California Labor Code §1776, the Contractor and each Subcontractor shall maintain Certified Payroll Records for labor employed by them to complete Project Work including: name, address, social security number, wage rates, work classification/trades, straight time and overtime hours worked each day and week, actual per diem wages paid. The Contractor and Subcontractors shall furnish copies of Certified Payroll Records to the District and others in accordance the Laws.

Certified Payroll Records of the Contractor and Subcontractors, in the form, format and within the times established by the Labor Commissioner, shall be submitted to the Labor Commissioner as required by the Laws. The District’s disbursement of any portion of the Contract Price is expressly conditioned on the Contractor’s completion and execution of the form of Verification of Certified Payroll Records Submittal to Labor Commissioner for the payment requested.

The District may deduct from the Contract Price and withhold disbursement of the Contract Price for any of the following: (i) Liquidated Damages; (ii) sums expended by the District to perform the Contractor’s obligations under the Contract Documents; (iii) defective or non-conforming Project Work not remedied; (iv) stop payment notice claims; (v) reasonable doubt that the Project can be completed for the unpaid balance of the Contract Price or within the Contract Time; (vi) unsatisfactory prosecution of the Project Work; (vii) unauthorized deviations from requirements of the Contract Documents; (ix) losses, damages or costs arising out of the Contractor’s default or breach of obligations; and (x) any other sums which the District is entitled or required to withhold from the Contractor the Contract Documents or the Laws. The failure by the District to deduct any of these sums from a progress payment shall not constitute a waiver of the District’s right to such sums.