8.1. Claims Resolution

Notwithstanding any claim, dispute, disagreement or other matter in controversy between the District and the Contractor relating to the Contract Documents or the Project Work, the Contractor shall continue to diligently prosecute and perform the Work, pending any final determination or decision regarding any such claim, dispute, disagreement or matter in controversy.

Claims of the Contractor are subject to the non-binding dispute resolution procedures set forth in Public Contract Code §9204 (“Section 9204”).

8.1.2.1. Contractor Claims

Contractor Claims are subject to the Section 9204 Procedures provided, however, that the Section 9204 Procedures are expressly subject to the Contractor’s prior full and timely compliance with requirements and procedures of the Contract Documents relating to submittal and resolution of Claims, change orders, disputes and other matters in controversy under the Contract Documents. By this reference, the Section 9204 Procedures are incorporated herein.

8.1.2.2. Subcontractor Claims

Subcontractor Claims are subject to Section 9204 Procedures, as modified herein. The District’s review of Subcontractor Claims is expressly subject to the Contractor’s submittal of a duly completed and executed form of Contractor Certification of Subcontractor Claim certifying that the Contractor has thoroughly reviewed the Subcontractor Claim and based on the Contractor’s review, certify that: (i) the Subcontractor Claim is made by the Subcontractor in good faith; (ii) the Subcontractor Claim is supported by reasonable documentation establishing entitlement to the relief requested and District liability therefor; and (iii) the Subcontractor Claim does not incorporate any request constituting a False Claim under applicable law, including the California False Claim Act (Government Code §12650 et seq.). The form of Contractor Certification of Subcontractor Claim is included in the Contract Documents.

Disputed Claims and other matters in controversy asserted by the Contractor against the District are a “suit for money or damages” and subject to Government Code §§945.4, 945.6 and 946 (“Government Code Claims Process”). An express condition precedent to the Contractor’s initiation of Section 20104.4 Dispute Resolution Procedures or Small Claims Court proceedings is the Contractor’s compliance with the Government Code Clams Process.

Claims not resolved by the Section 9204 Procedures are subject to Small Claims Court proceedings or binding dispute resolution procedures of Public Contract Code §20104.4 (Section 20104.4 Dispute Resolution Procedures).

8.1.4.1. Claims within Small Claims Court Jurisdiction

The exclusive tribunal for binding resolution of Disputed Claims valued at or less than the then current jurisdictional limits of the Small Claims Court. Venue for any Small Claims Court proceeding shall be the Small Claims Court designated for the geographic area of the Site.

8.1.4.2. Section 20104.4 Dispute Resolution Procedures; Claims Less than $375,000

Disputed Claims of $375,000 or less and more than the then current Small Claims Court jurisdictional limits shall be resolved in accordance with the civil action procedures established in Public Contract Code §20104.4. Mediation conducted pursuant to Section 9204 Procedures shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.

8.1.4.3. Limitation on Special/ Consequential Damages

In the event of the District’s breach or default of its obligations under the Contract Documents, the damages, if any, recoverable by the Contractor are limited to general damages directly caused by the breach or default and shall exclude any and all special or consequential damages, if any. The Contractor expressly waives and relinquishes any recovery of special or consequential damages from the District.

8.1.4.4. Attorneys' Fees

Except as expressly provided for in the Contract Documents, or authorized by the Laws, neither the District nor the Contractor shall recover from the other any attorneys’ fees or other costs associated with or arising out of any legal, administrative or other proceedings filed or instituted in connection with or arising out of the Contract Documents or the performance of either the District or the Contractor thereunder

Miscellaneous

The District shall have the right to review, audit, and to copy records and supporting documentation of the Contractor and Subcontractors relating to performance of the Contract. Contractor agrees to maintain such records for a minimum of three (3) years after final payment, unless a longer period of records retention is stipulated or required by the Laws. Contractor agrees to allow the District access to these records during normal business hours and to allow interviews of any employees who might reasonably have information related to such records. Contractor agrees to include a similar right of the District to audit records and interview staff in any Subcontract.

This Contract is governed by the laws of the state of California and shall be interpreted as a whole and not in favor of the District or the Contractor. Venue for any legal proceeding shall be the Superior Court for the County in which the Site is situated at the Superior Court branch situated closest to the Site.

The Contractor and District are excused from performance during the time and to the extent that they are prevented from obtaining, delivering, or performing by act of God, fire, strike, loss, or shortage of transportation facilities, lock-out, commandeering of materials, products, plants or facilities by the government, when satisfactory evidence thereof is presented to the other party, provided that it is satisfactorily established that the non-performance is not due to the fault or neglect of the party not performing.

This Contract shall be binding upon and inure to the benefit of the respective successors-in-interest of the District and the Contractor. The foregoing notwithstanding, the Contractor shall not assign by this Contract, any right or obligation hereunder or any portion thereof.

Unless otherwise stated in the Contract, all references to “days” shall be deemed references to calendar days.

Time is of the essence in performance and completion of obligations under the Contract.

The terms of the Contract shall be modified only by written instrument duly executed on behalf of the Contractor and District. No term or condition of the Contract shall be modified or amended except by a subsequent writing executed by the District and Contractor and approved or ratified by the District’s Board. Verbal or oral modifications to the Contract are not enforceable.

District's waiver or delayed enforcement of any term, condition, covenant or obligation of the Contractor under the Contract Documents shall not: (i) constitute the District’s waiver or modification of such term, condition, covenant or obligation; or (ii) limit, restrict or impair the District’s enforcement of such term, condition, covenant or obligation.

Provisions required by the Laws to be incorporated into the Contract Documents are deemed incorporated herein and the Contract Documents shall be read and enforced as though such provisions are incorporated herein.

In the event of conflict or inconsistency between the Contract and these Terms and Conditions (“Contract”) and the terms of Contractor’s Proposal, the terms of the Contract shall prevail over the Contractors Quote. It is further agreed that District's attachment of the Contractors Quote/Proposal shall not constitute a modification, amendment or limitation of any term or condition of the Contract unless such term or condition is expressly set forth in writing in this Contract.

If any provision of this Contract is declared or determined by any court of competent jurisdiction to be illegal, invalid or unenforceable, the legality, validity or enforceability of the remaining parts, terms and provisions shall not be affected thereby, and said illegal, unenforceable or invalid part, term or provision will be deemed not to be a part of this Contract.

While engaged in carrying out the terms and conditions of the Contract, the Contractor is an independent contractor, and not an officer, employee, agent, partner, or joint venture of the District.

VENDOR hereby warrants that any goods or services, including any hardware or software products or services, to be provided under the Purchase Order comply with the accessibility requirements of section 508 of the Rehabilitation Act of 1973, as amended (29 U.S.C. § 794d), including the Revised Section 508 Standards, and its implementing regulations set forth at Title 36, Code of Federal Regulations, Part 1194 (as amended), and applicable accessibility requirements under California Government Code §§ 11135 and 7405. VENDOR agrees to promptly respond to and resolve any complaint regarding accessibility of its products or services which is brought to its attention and will designate a contact person for expediting any complaints applicable to California Government Code §11135. VENDOR further agrees to indemnify, defend, and hold harmless the District, the Chancellor's Office of the California Community Colleges, and any California Community College using the VENDOR 's products or services from any claim arising out of its failure to comply with these requirements. Failure to comply with these requirements shall constitute a breach and be grounds for termination of the Purchase Order. VENDOR and any of their Subcontractors shall provide credible, third-party verification demonstrating compliance of product accessibility per current requirements of the revised US Section 508 Standards or Web Content Accessibility Guidelines (WCAG) 2.1 Level AA, or the most current version of WCAG Level AA adopted by the State of California or required under applicable federal law, upon initial deployment and with each major subsequent release prior to production use by faculty, staff, or students. Appropriate documentation detailing the testing, including evaluation results, will be current and maintained, and shall include a current and completed Voluntary Product Accessibility Template (VPAT) or Accessibility Conformance Report (ACR) and supporting test documentation upon request.

If the Work is subject, in whole or in part, to the California Division of the State Architect (DSA) jurisdiction, the Contractor shall completely and timely complete and/or comply with all DSA requirements related to: (i) observations/inspections of the Work during construction; and (ii) DSA PR 13-01 project inspections, tests and certification process. A material obligation of the Contractor hereunder is completion of all actions or activities required by a contractor for a work of improvement subject to DSA jurisdiction sufficient for DSA to issue a certification that the Work, as constructed, complies with the DSA approved Design Documents.

Unless otherwise expressly provided in the Contract Documents, the Contractor shall obtain and pay for all fees, permits or approvals necessary to complete the Work.

The terms of the Contract shall be modified only by written instrument duly executed on behalf of the Contractor and District. Verbal or oral modifications to the Contract of terms thereof are not valid or enforceable.

The Contractor and Subcontractors shall comply with District Policies prohibiting discriminatory practices against employees or prospective employees based on race, color, ancestry, national origin, religious creed, sex, age, sexual preference, marital status or other classification protected by the Laws. Contractor agrees to abide by this policy and to comply with Laws prohibiting discriminatory employment practices, including the California Fair Employment Practice Act.

The Contract Documents contain the entire agreement and understanding between the District and the Contractor concerning the subject matter hereof, and supersedes and replaces all prior negotiations, proposed contracts or amendments, whether written or oral.