Mission College Projects

Mission Projects

Construction projects and progress.

Facilities Master Plan

Version: May 2018

Construction Updates | September 2024

At-a-Glance

Original Base Contract Amount $72,244,800
Project Phase Design
Percent Complete Programming
Funding Measure W
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Programming May 2024
Design Build RFP/RFQ November 2024 | June 2025
Board Award July 2025
Design Phase July 2025
DSA Submission August 2026 | August 2027
Construction Start September 2027
Construction Completion September 2029
Closeout December 2029
Move-in Winter 2029

Key Contracts

Architect TBD (DBE)
Contractor TBD (DBE)
Project Manager Gilbane

Past Month’s Accomplishments

  • Project Programming meetings started

Next Month’s Milestones

  • Project definition established
  • RFP/RFQ document creation

Cost/Scope/Timeline Changes

None at this time.

At-a-Glance

Original Base Contract Amount $19,229,400
Project Phase Design
Percent Complete Programming
Funding Measure W
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Programming August 2024
Design Build RFP/RFQ March 2025 | October 2025
Board Award November 2025
Design Phase January 2026 | October 2026
DSA Submission November 2026 | April 2027
Construction Start May 2027
Construction Completion November 2028
Closeout December 2028
Move-in Winter 2028

Key Contracts

Architect TBD (DBE)
Contractor TBD (DBE)
Project Manager Gilbane

Past Month’s Accomplishments

  • Project Programming meetings started

Next Month’s Milestones

  • Project definition established
  • RFP/RFQ document creation

Cost/Scope/Timeline Changes

None at this time.

At-a-Glance

Original Base Contract Amount TBD
Project Phase Design
Percent Complete Programming
Funding Community Support Funds
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Programming May 2024
Design Phase
DSA Submission
Board Award
Construction Start
Construction Completion
Closeout
Move-in

Key Contracts

Architect P2S
Contractor TBD
Project Manager Gilbane

Past Month’s Accomplishments

  • District review of repair project scope from EOR

Next Month’s Milestones

  • EOR monitoring building usage for mechanical reporting/ design

Cost/Scope/Timeline Changes

None at this time.

At-a-Glance

Original Base Contract Amount $1,400,000
Project Phase Bidding
Percent Complete 100%
Funding Measure W
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion August 2024
DSA Approval June 2024
Board Award January 2025
Construction Start February 2025
Construction Completion November 2025
Closeout December 2025
Move-in

Key Contracts

Architect SVA Architects
Contractor TBD
Project Manager Gilbane

Past Month’s Accomplishments

  • Approval of DSA Addendum

Next Month’s Milestones

  • Close of Public Bid Effort

Cost/Scope/Timeline Changes

None at this time.

At-a-Glance

Original Base Contract Amount $55,000,000
Project Phase Pre-Construction
Percent Complete Bidding
Funding Measure W and State Funding
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion June 2023
DSA Approval November 2023
Board Award November 2024
Construction Start February 2025
Construction Completion February 2027
Closeout March 2027
Move-in March 2027

Key Contracts

Architect LPA
Contractor TBD
Project Manager Gilbane

Past Month’s Accomplishments

  • Contract documents uploaded on PlanetBids.

Next Month’s Milestones

  • Bid opening on September 17, 2024.

Cost/Scope/Timeline Changes

  • N/A

At-a-Glance

Original Base Contract Amount $3,743,505
Project Phase Construction
Percent Complete 69%
Funding Measure W and State Funding
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion
DSA Approval
Board Award May 2024
Construction Start July 2024
Construction Completion January 2025
Closeout February 2025
Move-in February 2025

Key Contracts

Architect Garland
Contractor Western Roofing Service
Project Manager Gilbane/Kitchell

Past Month’s Accomplishments

  • TAV, Science and Campus Center buildings completed.

Next Month’s Milestones

  • Hospitality Management and Locker Rooms to complete.

Cost/Scope/Timeline Changes

  • N/A

At-a-Glance

Original Base Contract Amount $16,018,622
Project Phase Construction
Percent Complete 5%
Funding Measure W
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion March 2023
DSA Approval February 2024
Board Award June 2024
Construction Start July 2024
Construction Completion September 2025
Closeout October 2025
Move-in Winter 2025

Key Contracts

Architect WRNS
Contractor SC Builders
Project Manager Gilbane

Past Month’s Accomplishments

  • Start of Construction Demolition
  • MEP Safe-off

Next Month’s Milestones

  • MEP Layout
  • SOG Trenching

Cost/Scope/Timeline Changes

N/A

At-a-Glance

Original Base Contract Amount $10,242,828
Project Phase Construction
Percent Complete 97%
Funding Measure W
Total Change Order Amount $2,460,484.87
Percent of Approved Change Orders 24% (DBE)

Schedule Milestones

Design Completion February 2021
DSA Approval February 2022
Board Award May 2019
Construction Start
Construction Completion November 2023
Closeout May 2024
Move-in May 2024

Key Contracts

Architect CURRENT Design Group
Contractor SunPower
Project Manager Gilbane

Past Month’s Accomplishments

  • The water lines investigation completed.

Next Month’s Milestones

  • SVP to issue permission to operate.
  • Hot Commissioning to start.
  • Solar system in Lot C to be energized.

Cost/Scope/Timeline Changes

  • Relocation of Capacitor Bank

At-a-Glance

Original Base Contract Amount $669,000
Project Phase Closeout
Percent Complete 100%
Funding Measure W
Total Change Order Amount $7,742
Percent of Approved Change Orders 1.16%

Schedule Milestones

Design Completion February 2023
DSA Approval June 2023
Board Award December 2023
Construction Start February 2024
Construction Completion June 2024
Closeout July 2024
Move-in August 2024

Key Contracts

Architect WRNS
Contractor Environmental Systems
Project Manager Gilbane

Past Month’s Accomplishments

  • Turnover Cx report to owner

Next Month’s Milestones

  • Prepare Notice of Completion

Cost/Scope/Timeline Changes

  • N/A

At-a-Glance

Original Base Contract Amount $6,442,000
Project Phase Closeout
Percent Complete 98%
Funding Measure W
Total Change Order Amount $538,850
Percent of Approved Change Orders 8%

Schedule Milestones

Design Completion November 2020
DSA Approval September 2021
Board Award December 2021
Construction Start December 2021
Construction Completion August 2023
Closeout September 2023
Move-in September 2023

Key Contracts

Architect Anderson Brule Architects
Contractor EF Brett & Company
Project Manager Gilbane Building Company

Past Month’s Accomplishments

  • Correction of the security system from pre-punch list

Next Month’s Milestones

  • Final Security testing

Cost/Scope/Timeline Changes

N/A