Future Facilities Plan
Version: July 2025
Future Facilities Plan
Version: July 2025
Construction Updates | October 2026
At-a-Glance
| Original Base Contract Amount | $29,204,336 |
| Project Phase | Design |
| Percent Complete | Construction Documentation |
| Funding | Measure W |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Schedule Milestones
| Programming | August 2024 |
| Design Build RFP/RFQ | March 2025 | July 2025 |
| Board Award | October 2025 |
| Design Phase | November 2025 | January 2027 |
| DSA Submission | December 2026 | June 2027 |
| Construction | June 2027 | August 2028 |
| Closeout | August 2028 | November 2028 |
| Move-in | February 2029 |
Project Approved Budget
| Initial | $19,299,400 ($5M from CIF) |
| Current | $19,299,400 |
Key Contracts
| Architect | Noll+Tam |
| Contractor | Rodan |
| Project Manager | Gilbane Building |
Project Scope
The project includes interior renovation of the Campus Center to enhance functionality and support evolving campus needs. The design-build delivery method allows for an integrated approach, and a carefully coordinated, multi-phased construction schedule to minimize disruption to building occupants.
Past Month’s Accomplishments
- Review of 50% Construction Documentation plans
Next Month’s Milestones
- Receipt of GMP and Early Buy-out Packages
- Completion of 50% CD plan review
Cost/Scope/Timeline Changes
- None

At-a-Glance
| Original Base Contract Amount | TBD |
| Project Phase | Design |
| Percent Complete | Construction Documents |
| Funding | Measure W / Capital Improvement Funds |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Schedule Milestones
| Programming | January 2025 |
| Design Phase | May 2025 | August 2026 |
| DSA Submission | August 2026 | December 2026 |
| Bidding | December 2026 | March 2027 |
| Board Award | February 2027 |
| Construction | March 2027 | August 2027 |
| Closeout | August 2027 | September 2027 |
| Move-in |
Key Contracts
| Architect | HPI |
| Contractor | TBD |
| Construction Manager | Gilbane |
Project Scope
The project includes improvements to enhance campus accessibility, security, and overall aesthetics along the north and west sides of campus; while maintaining a functional and efficient site layout. Planned elements include fencing, landscaping, signage enhancements, pedestrian access improvements, and service yard relocation to the south edge of campus.
Past Month’s Accomplishments
- Project submission to DSA
- Budget review
Next Month’s Milestones
- Complete review of Construction Documents
- Begin Preparation of Bid Documents
Cost/Scope/Timeline Changes
- N/A

At-a-Glance
| Original Base Contract Amount | $1,650,000 |
| Project Phase | Design |
| Percent Complete | Programming |
| Funding | Measure W / Capital Improvement Funds |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Schedule Milestones
| Programming | May 2024 |
| Design Phase | February 2025 |
| DSA Submission | |
| Board Award | |
| Construction Start | |
| Construction Completion | |
| Closeout | |
| Move-in |
Project Approved Budget
| Initial | $2,250,000 |
| Current | $2,250,000 |
Key Contracts
| Architect | P2S |
| Contractor | TBD |
| Construction Manager | Gilbane Building |
Project Scope
The project includes construction of an equipment pad to supplement the existing geothermal field serving the Gillmor Center. Proposed improvements include demolition of existing site elements, construction of a new boiler and chiller yard, connection to the existing Gillmor Center hydronic systems, and associated hardscape and landscape restoration.
Past Month’s Accomplishments
–
Next Month’s Milestones
- Design meetings restarted
Cost/Scope/Timeline Changes
- None

At-a-Glance
| Original Base Contract Amount | TBD |
| Project Phase | Design |
| Percent Complete | Bidding Documents |
| Funding | Capital Improvement Funds |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Projected Schedule Milestones
| Programming | November 2025 |
| Design Phase | April 2026 | June 2026 |
| DSA Submission | July 2026 | November 2026 |
| Bidding | November 2026 | December 2026 |
| Board Award | February 2027 |
| Construction | April 2027 | July 2027 |
| Closeout | August 2027 |
| Move-in |
Project Approved Budget
| Initial | $4,500,000 |
| Current | $4,500,000 |
Key Contracts
| Architect | Dialog Design |
| Contractor | TBD |
| Construction Manager | Gilbane Building |
Project Scope
The project includes design and replacement of the standing seam metal roof system and associated sheet metal building elements. Due to the nature of the building's construction this project requires structural and DSA review. This project will address on-going maintenance and water damage concerns.
Past Month’s Accomplishments
- DSA approval received
Next Month’s Milestones
- Preparation of Bid Documents
- Begin Procurement Coordination
Cost/Scope/Timeline Changes
- N/A

At-a-Glance
| Original Base Contract Amount | TBD |
| Project Phase | Design |
| Percent Complete | Construction Documents |
| Funding | Measure W |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Projected Schedule Milestones
| Programming | |
| Design Phase | November 2025 | June 2026 |
| DSA Submission | September 2026 | January 2027 |
| Bidding | January 2027 | March 2027 |
| Board Award | April 2027 |
| Construction | June 2027 | September 2027 |
| Closeout | October 2027 |
| Move-in |
Project Approved Budget
| Initial | TBD |
| Current | TBD |
Key Contracts
| Architect | Sandis |
| Contractor | TBD |
| Construction Manager | Gilbane Building |
Project Scope
The project includes implementation of pedestrian and traffic safety elements campus-wide. Design is intended to maintain an open and welcoming campus feel while ensuring separation of the vehicle traffic and pedestrian areas. Additionally, signage and traffic elements will be implemented to raise awareness and decrease vehicle speeds in areas of frequent vehicle/pedestrian conflicts.
Past Month’s Accomplishments
- Development of CD Drawings
Next Month’s Milestones
- Submission to DSA
- Preparation of Bid Documents
Cost/Scope/Timeline Changes
- N/A

At-a-Glance
| Original Base Contract Amount | $98,925,603 |
| Project Phase | Design |
| Percent Complete | Design Development |
| Funding | Measure W |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Schedule Milestones
| Programming | May 2024 |
| Design Build RFP/RFQ | November 2024 | June 2025 |
| Board Award | June 2025 |
| Design Phase | September 2025 | August 2026 |
| DSA Submission | August 2026 | February 2027 |
| Construction | January 2029 | April 2029 |
| Closeout | April 2029 | August 2029 |
| Move-in | April 2029 | July 2029 |
Project Approved Budget
| Initial | $135,000,000 |
| Current | $135,000,000 |
Key Contracts
| Architect | Gensler |
| Contractor | XL Construction |
| Construction Manager | Gilbane Building |
Project Scope
The district plans to develop an approximately 70,000 square-foot facility to expand its Science, Technology, Engineering, and Mathematics (STEM) lab spaces, including an event and conference center. Project scope includes renovation of the existing 32,000 square-foot Science Building. The project will be delivered using a progressive design-build approach.
Past Month’s Accomplishments
- Continue review 50% CD set of drawings
Next Month’s Milestones
- –
Cost/Scope/Timeline Changes
- Addition of HVAC unit replacement

At-a-Glance
| Original Base Contract Amount | $98,925,603 |
| Project Phase | Design |
| Percent Complete | Construction Documentation |
| Funding | Measure W |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Schedule Milestones
| Programming | May 2024 |
| Design Build RFP/RFQ | November 2024 | June 2025 |
| Board Award | June 2025 |
| Design Phase | September 2025 | November 2026 |
| DSA Submission | November 2026 | July 2027 |
| Construction | April 2027 | January 2029 |
| Closeout | January 2029 | May 2029 |
| Move-in | January 2029 |
Project Approved Budget
| Initial | $135,000,000 |
| Current | $135,000,000 |
Key Contracts
| Architect | Gensler |
| Contractor | XL Construction |
| Construction Manager | Gilbane Building |
Project Scope
The district plans to develop an approximately 70,000 square-foot facility to expand its Science, Technology, Engineering, and Mathematics (STEM) lab spaces, including an event and conference center. Project scope includes renovation of the existing 32,000 square-foot Science Building. The project will be delivered using a progressive design-build approach.
Past Month’s Accomplishments
- Review 50% CD planset
Next Month’s Milestones
- Begin review of 75% CDs
Cost/Scope/Timeline Changes
- Expansion of site improvements

At-a-Glance
| Original Base Contract Amount | $900,000 |
| Project Phase | Bidding |
| Percent Complete | 0% |
| Funding | Measure W |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Projected Schedule Milestones
| Programming | October 2024 | April 2025 |
| Design Phase | May 2025 | November 2025 |
| DSA Submission | |
| Construction Award | December 2026 |
| Construction | January 2027 | April 2027 |
| Closeout | May 2027 |
| Move-in |
Project Approved Budget
| Initial | $1,935,000 |
| Current | $1,935,000 |
Key Contracts
| Architect | SOBE/ Catalyst |
| Contractor | TBD |
| Construction Manager | Gilbane Building |
Project Scope
The project includes upgrade of security infrastructure in and around the Information Systems and Campus Center Buildings. The scope of work includes replacing outdated security systems, installing additional security cameras, and upgrading door hardware to enhance overall campus safety.
Past Month’s Accomplishments
- Investigate CollegeBuys procurement
Next Month’s Milestones
- Reviewing procurement approach
Cost/Scope/Timeline Changes
- N/A

At-a-Glance
| Original Base Contract Amount | $1,465,000 |
| Project Phase | Construction |
| Percent Complete | 99% |
| Funding | Measure W / Capital Improvement Funds |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Projected Schedule Milestones
| Programming | October 2025 |
| Design Phase | November 2025 | January 2026 |
| DSA Submission | |
| Bidding | January 2026 | April 2026 |
| Board Award | May 2026 |
| Construction | July 2026 | September 2026 |
| Closeout | October 2026 |
| Move-in |
Project Approved Budget
| Initial | $10,500,000 (All Roofing Projects) |
| Current | $$10,500,000 |
Key Contracts
| Architect | Garland Roofing |
| Contractor | Courtney, Inc. |
| Construction Manager | Gilbane Building |
Project Scope
The project includes restoration of the Gillmor and IS Building roofs with a waterproof sealant and new detailing at all existing building elements. Restoration will carry a new 20-year warranty for these buildings' roofs.
Past Month’s Accomplishments
- Final Acceptance
Next Month’s Milestones
- Project Closeout
Cost/Scope/Timeline Changes
- N/A
At-a-Glance
| Original Base Contract Amount | $366,061 |
| Project Phase | Construction |
| Percent Complete | 75% |
| Funding | Capital Improvement Funds |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Projected Schedule Milestones
| Programming | October 2025 |
| Design Phase | November 2025 | January 2026 |
| DSA Submission | |
| Bidding | January 2026 | April 2026 |
| Board Award | May 2026 |
| Construction | September 2026 | December 2026 |
| Closeout | January 2027 |
| Move-in |
Project Approved Budget
| Initial | $10,500,000 (All Roofing Projects) |
| Current | $10,500,000 |
Key Contracts
| Architect | Garland Roofing |
| Contractor | Andy's Roofing |
| Construction Manager | Gilbane Building |
Project Scope
The project includes replacement of the Art Annex and Gillmor patio roofing systems with new waterproofing systems and new detailing at all existing building elements. Replacement will carry a new 30-year warranty for these buildings' roofing systems.
Past Month’s Accomplishments
- Completion of Art Annex Roof
Next Month’s Milestones
- Commencement of Gillmor Patio Roof Project final completion
Cost/Scope/Timeline Changes
- N/A

At-a-Glance
| Original Base Contract Amount | $16,018,622 |
| Project Phase | Construction |
| Percent Complete | 95% |
| Funding | Measure W |
| Total Change Order Amount | $2,696,142.75 |
| Percent of Approved Change Orders | 16.8% |
Projected Schedule Milestones
| Programming | |
| Design Phase | April 2022 | November 2023 |
| DSA Submission | |
| Bidding | March 2024 | June 2024 |
| Board Award | |
| Construction Start | July 2024 | October 2026 |
| Closeout | October 2026 | December 2026 |
| Move-in |
Project Approved Budget
| Initial | $18,523,800 |
| Current | $28,505,030 |
Key Contracts
| Architect | WRNS |
| Contractor | SC Builders |
| Construction Manager | Gilbane Building |
Project Scope
The project includes renovation of the existing Library space to a facility that supports studying, collaboration, and socializing. Improvements include an outdoor reading garden, 11 rooms for group study, and student gathering spaces. Reduced book stacks and repositioned administrative spaces create open, light-filled areas, fostering connection and academic growth. Replacement of existing mechanical, power, and data infrastructure will extend the renovated facility's usable life.
Past Month’s Accomplishments
- Open to Public
Next Month’s Milestones
- Reading Garden Competition
- Landscaping and Irrigation Finalization
Cost/Scope/Timeline Changes
- Encroachment permit
- Curtain wall detail changes
At-a-Glance
| Original Base Contract Amount | $1,072,000 |
| Project Phase | Construction |
| Percent Complete | 40% |
| Funding | Measure W / Capital Improvement Funds |
| Total Change Order Amount | $0 |
| Percent of Approved Change Orders | 0% |
Projected Schedule Milestones
| Programming | September 2024 | October 2024 |
| Design Phase | August 2024 | July 2025 |
| DSA Submission | August 2025 | December 2025 |
| Bidding | January 2026 | April 2026 |
| Board Award | April 2026 |
| Construction | October 2026 | January 2027 |
| Closeout | January 2027 | February 2027 |
| Move-in |
Project Approved Budget
| Initial | $2,500,000 |
| Current | $2,500,000 |
Key Contracts
| Architect | SVA |
| Contractor | Atlas-Pellizari Electric |
| Construction Manager | Gilbane |
Project Scope
The project includes the removal of the existing Tennis Court's light poles, new power infrastructure, and installation of new concrete foundations, light poles, and lighting controls. The new light poles will be placed on the perimeter of the tennis courts and are specially designed for athletic courts and fields.
Past Month’s Accomplishments
- Commencement of underground electrical pathway
- Shop fabrication of light poles
Next Month’s Milestones
- Delivery and Installation of light poles
Cost/Scope/Timeline Changes
- N/A

At-a-Glance
| Original Base Contract Amount | $6,442,000 |
| Project Phase | Closeout |
| Percent Complete | 99% |
| Funding | Measure W |
| Total Change Order Amount | $538,850 |
| Percent of Approved Change Orders | 8% |
Schedule Milestones
| Programming | |
| Design Phase | August 2019 | November 2020 |
| DSA Approval | September 2021 |
| Bidding | October 2021 | December 2021 |
| Board Award | December 2021 |
| Construction | December 2021 | August 2023 |
| Closeout | September 2023 |
| Move-in |
Project Approved Budget
| Initial | |
| Current | $$10,068,056 |
Key Contracts
| Architect | Anderson Brule Architects |
| Contractor | EF Brett & Company |
| Construction Manager | Gilbane Building |
Project Scope
This project will renovate the existing 10,234 square foot, one-story CDC building, including upgrades to the play yard. The work will include upgrades to the roof, HVAC, lighting, flooring, ceiling, data/telecommunication, electrical, seismic work, ADA accessibility, play yard upgrades and interior remodeling to meet the program requirements of the college.
Past Month’s Accomplishments
- Completion of security as-builts
Next Month’s Milestones
- Security punch list back check
Cost/Scope/Timeline Changes
- N/A