At-a-Glance
Original Base Contract Amount |
$72,244,800 |
Project Phase |
Design |
Percent Complete |
Programming |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
May 2024 |
Design Build RFP/RFQ |
November 2024 | June 2025 |
Board Award |
July 2025 |
Design Phase |
July 2025 |
DSA Submission |
August 2026 | August 2027 |
Construction Start |
September 2027 |
Construction Completion |
September 2029 |
Closeout |
December 2029 |
Move-in |
Winter 2029 |
Key Contracts
Architect |
TBD (DBE) |
Contractor |
TBD (DBE) |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Project Programming meetings started
Next Month’s Milestones
- Project definition established
- RFP/RFQ document creation
Cost/Scope/Timeline Changes
None at this time.
At-a-Glance
Original Base Contract Amount |
$19,229,400 |
Project Phase |
Design |
Percent Complete |
Programming |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
August 2024 |
Design Build RFP/RFQ |
March 2025 | October 2025 |
Board Award |
November 2025 |
Design Phase |
January 2026 | October 2026 |
DSA Submission |
November 2026 | April 2027 |
Construction Start |
May 2027 |
Construction Completion |
November 2028 |
Closeout |
December 2028 |
Move-in |
Winter 2028 |
Key Contracts
Architect |
TBD (DBE) |
Contractor |
TBD (DBE) |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Project Programming meetings started
Next Month’s Milestones
- Project definition established
- RFP/RFQ document creation
Cost/Scope/Timeline Changes
None at this time.
At-a-Glance
Original Base Contract Amount |
TBD |
Project Phase |
Design |
Percent Complete |
Programming |
Funding |
Community Support Funds |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
May 2024 |
Design Phase |
|
DSA Submission |
|
Board Award |
|
Construction Start |
|
Construction Completion |
|
Closeout |
|
Move-in |
|
Key Contracts
Architect |
P2S |
Contractor |
TBD |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- District review of repair project scope from EOR
Next Month’s Milestones
- EOR monitoring building usage for mechanical reporting/ design
Cost/Scope/Timeline Changes
None at this time.
At-a-Glance
Original Base Contract Amount |
$1,400,000 |
Project Phase |
Bidding |
Percent Complete |
100% |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Design Completion |
August 2024 |
DSA Approval |
June 2024 |
Board Award |
January 2025 |
Construction Start |
February 2025 |
Construction Completion |
November 2025 |
Closeout |
December 2025 |
Move-in |
|
Key Contracts
Architect |
SVA Architects |
Contractor |
TBD |
Project Manager |
Gilbane |
Past Month’s Accomplishments
Next Month’s Milestones
- Close of Public Bid Effort
Cost/Scope/Timeline Changes
None at this time.
At-a-Glance
Original Base Contract Amount |
$55,000,000 |
Project Phase |
Pre-Construction |
Percent Complete |
Bidding |
Funding |
Measure W and State Funding |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Design Completion |
June 2023 |
DSA Approval |
November 2023 |
Board Award |
November 2024 |
Construction Start |
February 2025 |
Construction Completion |
February 2027 |
Closeout |
March 2027 |
Move-in |
March 2027 |
Key Contracts
Architect |
LPA |
Contractor |
TBD |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Contract documents uploaded on PlanetBids.
Next Month’s Milestones
- Bid opening on September 17, 2024.
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
$3,743,505 |
Project Phase |
Construction |
Percent Complete |
69% |
Funding |
Measure W and State Funding |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Design Completion |
|
DSA Approval |
|
Board Award |
May 2024 |
Construction Start |
July 2024 |
Construction Completion |
January 2025 |
Closeout |
February 2025 |
Move-in |
February 2025 |
Key Contracts
Architect |
Garland |
Contractor |
Western Roofing Service |
Project Manager |
Gilbane/Kitchell |
Past Month’s Accomplishments
- TAV, Science and Campus Center buildings completed.
Next Month’s Milestones
- Hospitality Management and Locker Rooms to complete.
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
$16,018,622 |
Project Phase |
Construction |
Percent Complete |
5% |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Design Completion |
March 2023 |
DSA Approval |
February 2024 |
Board Award |
June 2024 |
Construction Start |
July 2024 |
Construction Completion |
September 2025 |
Closeout |
October 2025 |
Move-in |
Winter 2025 |
Key Contracts
Architect |
WRNS |
Contractor |
SC Builders |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Start of Construction Demolition
- MEP Safe-off
Next Month’s Milestones
Cost/Scope/Timeline Changes
N/A
At-a-Glance
Original Base Contract Amount |
$10,242,828 |
Project Phase |
Construction |
Percent Complete |
97% |
Funding |
Measure W |
Total Change Order Amount |
$2,460,484.87 |
Percent of Approved Change Orders |
24% (DBE) |
Schedule Milestones
Design Completion |
February 2021 |
DSA Approval |
February 2022 |
Board Award |
May 2019 |
Construction Start |
|
Construction Completion |
November 2023 |
Closeout |
May 2024 |
Move-in |
May 2024 |
Key Contracts
Architect |
CURRENT Design Group |
Contractor |
SunPower |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- The water lines investigation completed.
Next Month’s Milestones
- SVP to issue permission to operate.
- Hot Commissioning to start.
- Solar system in Lot C to be energized.
Cost/Scope/Timeline Changes
- Relocation of Capacitor Bank
At-a-Glance
Original Base Contract Amount |
$669,000 |
Project Phase |
Closeout |
Percent Complete |
100% |
Funding |
Measure W |
Total Change Order Amount |
$7,742 |
Percent of Approved Change Orders |
1.16% |
Schedule Milestones
Design Completion |
February 2023 |
DSA Approval |
June 2023 |
Board Award |
December 2023 |
Construction Start |
February 2024 |
Construction Completion |
June 2024 |
Closeout |
July 2024 |
Move-in |
August 2024 |
Key Contracts
Architect |
WRNS |
Contractor |
Environmental Systems |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Turnover Cx report to owner
Next Month’s Milestones
- Prepare Notice of Completion
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
$6,442,000 |
Project Phase |
Closeout |
Percent Complete |
98% |
Funding |
Measure W |
Total Change Order Amount |
$538,850 |
Percent of Approved Change Orders |
8% |
Schedule Milestones
Design Completion |
November 2020 |
DSA Approval |
September 2021 |
Board Award |
December 2021 |
Construction Start |
December 2021 |
Construction Completion |
August 2023 |
Closeout |
September 2023 |
Move-in |
September 2023 |
Key Contracts
Architect |
Anderson Brule Architects |
Contractor |
EF Brett & Company |
Project Manager |
Gilbane Building Company |
Past Month’s Accomplishments
- Correction of the security system from pre-punch list
Next Month’s Milestones
Cost/Scope/Timeline Changes
N/A