At-a-Glance
Original Base Contract Amount |
$72,244,800 |
Project Phase |
Design |
Percent Complete |
Programming |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
May 2024 |
Design Build RFP/RFQ |
November 2024 | June 2025 |
Board Award |
June 2025 |
Design Phase |
July 2025 | July 2026 |
DSA Submission |
August 2026 | August 2027 |
Construction Start |
September 2027 |
Construction Completion |
September 2029 |
Closeout |
December 2029 |
Move-in |
Winter 2029 |
Key Contracts
Architect |
TBD (DBE) |
Contractor |
TBD (DBE) |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Selection of shortlist firms
- Issuance of RFP
Next Month’s Milestones
- RFP meetings with DBE team’s
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
$19,229,400 |
Project Phase |
Design |
Percent Complete |
Programming |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
August 2024 |
Design Build RFP/RFQ |
March 2025 | July 2025 |
Board Award |
August 2025 |
Design Phase |
January 2026 | October 2026 |
DSA Submission |
November 2026 | April 2027 |
Construction Start |
May 2027 |
Construction Completion |
November 2028 |
Closeout |
December 2028 |
Move-in |
Winter 2028 |
Key Contracts
Architect |
TBD (DBE) |
Contractor |
TBD (DBE) |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Project definition established
- RFQ issued
Next Month’s Milestones
- RFP documentation finalized
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
TBD |
Project Phase |
Design |
Percent Complete |
95% Construction Drawings |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
January 2025 |
Design Phase |
October 2024 | April 2025 |
Bidding |
May 2025 | July 2025 |
Construction Start |
August 2025 |
Construction Completion |
November 2025 |
Closeout |
November 2025 |
Key Contracts
Architect |
Catalyst |
Contractor |
TBD |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Review of 95% Construction Drawings
Next Month’s Milestones
- Bid Calendar approval
- Creation of bid documents
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
TBD |
Project Phase |
Design |
Percent Complete |
95% Construction Drawings |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
October 2024 |
Design Phase |
October 2024 |
Bidding |
May 2025 | July 2025 |
Construction Start |
August 2025 |
Construction Completion |
November 2025 |
Closeout |
December 2025 |
Key Contracts
Architect |
Catalyst |
Contractor |
TBD |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Review of 95% Construction Drawings
Next Month’s Milestones
- Bid Calendar approval
- Creation of bid documents
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
TBD |
Project Phase |
Design |
Percent Complete |
Programming |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
May 2024 |
Design Phase |
February 2025 |
DSA Submission |
|
Board Award |
|
Construction Start |
|
Construction Completion |
|
Closeout |
|
Move-in |
|
Key Contracts
Architect |
P2S |
Contractor |
TBD |
Project Manager |
Gilbane |
Past Month’s Accomplishments
Next Month’s Milestones
- Process design team’s proposal
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
TBD |
Project Phase |
Design |
Percent Complete |
Programming |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
September 2024 | October 2024 |
Design Phase |
November 2024 |
DSA Submission |
|
Board Award |
|
Construction Start |
|
Construction Completion |
|
Closeout |
|
Move-in |
|
Key Contracts
Architect |
SVA |
Contractor |
TBD |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Boring and soil sampling completed
Next Month’s Milestones
- Receive the Geotech report
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
TBD |
Project Phase |
Design |
Percent Complete |
Programming |
Funding |
Measure W / CSF |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
January 2025 |
Design Phase |
|
Bidding |
|
Construction Start |
|
Construction Completion |
|
Closeout |
|
Key Contracts
Architect |
HPI |
Contractor |
TBD |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Reviewed concept images of improvements
Next Month’s Milestones
- Review updated concepts for expanded project boundaries
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
TBD |
Project Phase |
Bidding |
Percent Complete |
100% Construction Drawings |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Programming |
|
Design Phase |
February 2025 |
Bidding |
March 2025 |
Construction Start |
June 2025 |
Construction Completion |
|
Closeout |
September 2025 |
Key Contracts
Architect |
Sandis |
Contractor |
TBD |
Project Manager |
Gilbane |
Past Month’s Accomplishments
Next Month’s Milestones
Cost/Scope/Timeline Changes
At-a-Glance
Original Base Contract Amount |
$1,398,000 |
Project Phase |
Construction |
Percent Complete |
0% |
Funding |
Measure W |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Design Completion |
April 2024 |
DSA Approval |
June 2024 |
Board Award |
January 2025 |
Construction Start |
March 2025 |
Construction Completion |
November 2025 |
Closeout |
December 2025 |
Key Contracts
Architect |
SVA Architects |
Contractor |
Bear Electrical Solutions |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- Contract Issuance
- NTP issuance
Next Month’s Milestones
- Pre-Construction Kick-off
- Campus coordination
Cost/Scope/Timeline Changes
- Ticket machine pad pricing
At-a-Glance
Original Base Contract Amount |
$10,242,828 |
Project Phase |
Construction |
Percent Complete |
97% |
Funding |
Measure W |
Total Change Order Amount |
$2,460,485 |
Percent of Approved Change Orders |
24% (DBE) |
Schedule Milestones
Design Completion |
February 2021 |
DSA Approval |
February 2022 |
Board Award |
May 2019 |
Construction Start |
March 2022 |
Construction Completion |
April 2025 |
Closeout |
May 2025 |
Key Contracts
Architect |
CURRENT Design Group |
Contractor |
TEDGUSA |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- SunPower name change to TEDGUSA
Next Month’s Milestones
- District approval for Interconnection agreement
- SVP permission to operate
Cost/Scope/Timeline Changes
- Relocation of Capacitor Bank
At-a-Glance
Original Base Contract Amount |
$16,018,622 |
Project Phase |
Construction |
Percent Complete |
21% |
Funding |
Measure W |
Total Change Order Amount |
$57,128 |
Percent of Approved Change Orders |
0.36% |
Schedule Milestones
Design Completion |
March 2023 |
DSA Approval |
February 2024 |
Board Award |
June 2024 |
Construction Start |
July 2024 |
Construction Completion |
September 2025 |
Closeout |
October 2025 |
Move-in |
January 2026 |
Key Contracts
Architect |
WRNS |
Contractor |
SC Builders |
Project Manager |
Gilbane |
Past Month’s Accomplishments
- MEP in-wall rough-in
- Demo existing rooftop AHU
Next Month’s Milestones
- Drywall install
- MEP overhead rough-in inspections
- TAV FACP Relocation
Cost/Scope/Timeline Changes
- Installation of HVAC rooftop units
- Mural design changes
At-a-Glance
Original Base Contract Amount |
$3,743,505 |
Project Phase |
Close-out |
Percent Complete |
100% |
Funding |
Measure W and State Funding |
Total Change Order Amount |
$0 |
Percent of Approved Change Orders |
0% |
Schedule Milestones
Design Completion |
|
DSA Approval |
|
Board Award |
May 2024 |
Construction Start |
July 2024 |
Construction Completion |
January 2025 |
Closeout |
February 2025 |
Key Contracts
Architect |
Garland |
Contractor |
Western Roofing Service |
Project Manager |
Gilbane/Kitchell |
Past Month’s Accomplishments
Next Month’s Milestones
Cost/Scope/Timeline Changes
- Repair of damaged insulation on Gym
At-a-Glance
Original Base Contract Amount |
$6,442,000 |
Project Phase |
Closeout |
Percent Complete |
99% |
Funding |
Measure W |
Total Change Order Amount |
$538,850 |
Percent of Approved Change Orders |
8% |
Schedule Milestones
Design Completion |
November 2020 |
DSA Approval |
September 2021 |
Board Award |
December 2021 |
Construction Start |
December 2021 |
Construction Completion |
August 2023 |
Closeout |
September 2023 |
Move-in |
September 2023 |
Key Contracts
Architect |
Anderson Brule Architects |
Contractor |
EF Brett & Company |
Project Manager |
Gilbane Building Company |
Past Month’s Accomplishments
- Security punch list corrections complete
Next Month’s Milestones
- Security punch list back check
Cost/Scope/Timeline Changes